You are here: System Overview > TAC Heater/Cooler > Installation > Install the Gas Ring

Install the Gas Ring

  1. Install the gas ring by placing it around the heater element on the Heater/Cooler base as shown in Figure 1. Orient the clearance groove in the bottom of the gas ring over the barb cooling water fittings. The magnets will hold it in place.
CAUTION: Do not hit the Heater/Cooler element. It is fragile.

Figure 1: The heater/cooler gas ring attached to the heater/cooler base. Dimension 3100/V shown.

  1. Connect the gas inlet:

Figure 2: Dimension Icon/Edge manifold, rear view

  1. Connect the other end of this tubing to one of the barb fittings on the gas ring.

Figure 3: Run water and gas cables through clamps on top of manifold to provide a service loop.

  1. Supply the gas to the flow meter:

 

www.bruker.com Bruker Corporation
www.brukerafmprobes.com 112 Robin Hill Rd.
nanoscaleworld.bruker-axs.com/nanoscaleworld/ Santa Barbara, CA 93117
   
  Customer Support: (800) 873-9750
  Copyright 2010, 2011. All Rights Reserved.